Tuesday, April 27, 2010

Update Meeting Held April 26


A meeting with residents, families and staff took place Monday, April 26. Mike Kearney, ED, RIch Bottone, VP for Development and Carmel Roques, COO, explained current progress and what is to come in the near future.

Due to the need to completely remove all of the insulation in the attic and move various electrical wires throughout the attic space, the roof part of the project will not begin until June. It is still targeted for completion in November, so once the roofers begin it will move much more quickly than originally thought.

Insulation was removed last week (see picture) from over the Health Center.
Painting has begun in HC 14 and is moving along on schedule. Also in two of the private rooms we were able to have the enlarged ADA bathrooms.